KGRTC New Learning Centre Project
Progress Level - (Project in Progress): The final detailed design report including full architectural and engineering designs, work specifications, construction plans, implementation schedules tender documents comprising bills of quantities, forms of contracts and project cost estimates have been submitted, reviewed and approved. Construction cost's are estimated to be USD20,705,528.55 and the construction period will last for 3 Years. The EPB was approved by ZEMA and drawings were approved by Choma local planning authority.